Solaredge Hd-wave Inverters With Built-in Rgm Instruction Manual

HD-Wave Inverters with Built-In RGM

Product Information

The SolarEdge HD-Wave Inverter is a high-performance inverter
with built-in production RGM (Revenue Grade Meter) and consumption
monitoring capabilities. It supports revenue grade (C12.20)
production metering and requires the installation of one or two
external CTs (Current Transformers) for the consumption monitoring
function.

Version: 1.1, January 2021

Product Usage Instructions

Installation Prerequisites

  • The inverter must be a SetApp-enabled inverter.
  • The inverter must have one of the following part numbers:
  • SExxxxH-US000BxI4: Single phase inverter with HD-wave
    technology
  • SExxxxH-US000Bx34: EV-charging single phase inverter
  • SExxxxH-USS3BBx14: StorEdge inverter with HD-Wave
    technology

Required Equipment

The following equipment is required for the installation:

  • Current Transformers (CTs), purchased separately from
    SolarEdge:
    • Slim CTs: SECT-SPL-225A-T-20
    • Split core CTs: SEACT0750-200NA-20, SEACT1250-400NA-20
  • Adapter cable required for non-neutral grids, purchased
    separately from SolarEdge: ADPTR-CABLE-KIT-K1 (5 units per
    package)
  • Twisted pair CT Extension cable, to be purchased separately.
    The required cable length depends on the distance between the
    inverter and the service panel, but should not exceed 21 feet.
    Cable requirements are as follows:
    • Twisted pairs
    • Voltage Rating: 600V
    • Minimum gauge: 24 AWG
    • Maximum gauge: 14 AWG
  • Shielded CT Extension cable, to be purchased separately. The
    shielded extension cable connects the CT to the inverter via the AC
    conduit. The required cable length depends on the distance between
    the inverter and the service panel. Cable requirements are as
    follows:
    • Shielded cable containing two twisted pairs (one per CT)
    • Voltage Rating: 600V
    • Minimum gauge: 24 AWG
    • Maximum gauge: 14 AWG

CT Installation

The CT(s) are wired via the AC conduit along with the AC wires.
Follow the connection diagrams below to wire the meter:

CTs in a Split-Phase Grid with Neutral

In a split-phase grid with neutral, two CTs are installed as
illustrated in Figure 1.

Split Phase Grid with Neutral

CTs in a Split-Phase Grid without Neutral

In a split-phase grid without neutral, one CT is installed as
illustrated in Figure 2.

Split Phase Grid without Neutral

Installing the CTs

  1. Power off the inverter and disconnect its main circuit
    breaker.
  2. Attach the CTs to the relevant AC wires:
  • For distances of up to 21 feet between the inverter and the
    service panel, a twisted pair lead wire can be used.
  • For distances of over 21 feet between the inverter and the
    service panel, attach the CTs to the relevant AC wires as shown in
    the diagrams above.
  • When attaching the CT to the conductor to be measured, ensure
    that the arrow on the CT points in the direction of the current
    source.
  • Cut the CT’s black-and-white twisted wire pair to the required
    length (leaving some additional spare length), and connect the pair
    to the shielded CT extension cable (CAT5e or any other shielded
    wire) using a crimping tool.

    Version 1.1, January 2021 1
    Application Note ­ HD-Wave Inverters with Built-In RGM & Consumption Monitoring for North America
    Version History
    Version 1.1, January 2021 ­ new slim-profile CT Version 1.0, March 2020 ­ first version
    Contents
    Application Note ­ HD-Wave Inverters with Built-In RGM & Consumption Monitoring for North America ……………………………………………………… 1 Introduction …………………………………………………………………………………………………………………………………………………………………………………………………………………………….. 1 Installation Prerequisites ………………………………………………………………………………………………………………………………………………………………………………………………………. 2 Required Equipment ……………………………………………………………………………………………………………………………………………………………………………………………………………… 2 CT Installation …………………………………………………………………………………………………………………………………………………………………………………………………………………………. 3 Configuration ………………………………………………………………………………………………………………………………………………………………………………………………………………………….. 7 Monitoring the Meter ……………………………………………………………………………………………………………………………………………………………………………………………………………. 8 Meter Specification ………………………………………………………………………………………………………………………………………………………………………………………………………………… 9
    Introduction
    The SolarEdge HD-Wave Inverter with built-in production RGM and consumption monitoring supports revenue grade (C12.20) production metering. The consumption function requires the installation of one or two external CTs. This application note describes how to prepare the inverter for consumption monitoring.

    2
    Installation Prerequisites
    The following conditions are required for the inverter to support the consumption monitoring option:
    The inverter must be a SetApp-enabled inverter.
    The inverter must have one of the following part numbers:
    SExxxxH-US000BxI4: Single phase inverter with HD-wave technology SExxxxH-US000Bx34: EV-charging single phase inverter SExxxxH-USS3BBx14: StorEdge inverter with HD-Wave technology
    Required Equipment
    Current Transformers (CTs) , purchased separately from SolarEdge, 20 units per package:
    Slim CTs: SECT-SPL-225A-T-20 Split core CTs: SEACT0750-200NA-20, SEACT1250-400NA-20
    Adapter cable required for non-neutral grids, purchased separately from SolarEdge: ADPTR-CABLE-KIT-K1 (5 units per package)
    Twisted pair CT Extension cable, to be purchased separately. The required cable length depends on the distance between the inverter and the service panel, but should not exceed 21 feet. Cable requirements are as follows:
    Twisted pairs Voltage Rating: 600V Minimum gauge: 24 AWG Maximum gauge: 14 AWG
    Shielded CT Extension cable, to be purchased separately. The shielded extension cable connects the CT to the inverter via the AC conduit. The required cable length depends on the distance between the inverter and the service panel. Cable requirements are as follows:
    Shielded cable containing two twisted pairs (one per CT) Voltage Rating: 600V Minimum gauge: 24 AWG Maximum gauge: 14 AWG

    3
    CT Installation
    The wiring that connects the CT(s) to the meter is routed via the AC conduit, together with the AC wires. The CT-to-meter wiring requires use of a shielded CT extension cable. Wire the meter in accordance with one of the connection diagrams below:
    Split-phase grid with neutral Split-phase grid without neutral
    CTs in a Split-Phase Grid with Neutral
    In a split-phase grid with neutral, two CTs are installed as illustrated in the figure below.
    Figure 1: Split Phase Grid with Neutral
    CTs in a Split-Phase Grid without Neutral
    In a split-phase grid without neutral, one CTs is installed as illustrated in the figure below.
    Figure 2: Split Phase Grid without Neutral

    4
    Installing the CTs
    To install the CTs: 1. Power off the inverter and disconnect its main circuit breaker. 2. Attach the CTs as to the relevant AC wires:
    For distances of up to 21 feet between the inverter and the service panel, a twisted pair lead wire can be used. For distances of over 21 feet between the inverter and the service panel, attach the CTs to the relevant AC wires as shown in the diagrams above.
    NOTE
    When attaching the CT to the conductor to be measured, the arrow on the CT should point in the direction of the current source. 3. Cut the CT’s black-and-white twisted wire pair to the required length (leaving some additional spare length), and connect the pair to the shielded CT extension cable (CAT5e or any other shielded wire), splicing them using a crimping tool, as shown in the figure below.
    Figure 3: Connecting the CT wires to the shielded CT extension cable
    NOTE
    Do not use the method of twisting the wires and taping them together. This type of connection is not reliable and the wires may eventually disconnect from each other. 4. Connect the AC wiring ­ L1, L2, and N (if required) ­ to the designated terminal block as shown in Figure 4 below.

    5 5. Run the shielded extension CT cable in the AC conduit and through the knockout of the DC Safety Unit.
    NOTE
    The CT’s twisted pair should not be run via the AC conduit, as this will affect the quality of the measurements. Only shielded wire should be run in the AC conduit.
    Figure 4: AC and CT Wiring Diagram
    NOTE
    The above figure shows only the wiring that is to be connected by the installer. Factory pre-wired meter cabling does not appear in the diagram.

    6 6. Connect the CT wires from the shielded extension cable to the meter. Make sure to connect each phase’s CT to the corresponding
    meter terminal blocks (L1 CT and L2 CT), as shown in the figure below.
    NOTE
    The CT extension cable’s shielding should be left unconnected at both ends.
    Figure 5: Connecting the CT Wires to the Meter
    NOTE
    The meter’s RS485 wiring is factory pre-installed and should be left unchanged. 7. In a non-neutral grid, take the following actions:
    Make sure that only the L1 and L2 wires are connected to the AC terminal block (N should not be connected). Make sure that only one CT is installed. It should be connected to the L1 CT terminal block, as shown in Figure 2 above. Detach the AC terminal block from the meter, and attach the non-neutral grid adapter cable in its place. Then attach the AC
    terminal block to the other side of the adapter cable, as shown in Figure 6.
    NOTE
    The non-neutral grid adapter cable (ADPTR-CABLE-KIT-K1) is not supplied with the inverter and must be purchased separately. For more information, contact your SolarEdge representative.
    Figure 6: For non-neutral grid: Insert the adapter cable between the meter’s AC socket and the wired AC terminal block

    7
    Configuration
    The meter’s factory default function setting is Inverter Production + E/I. Production metering is operational at all times (as long as inverter is powered on). The consumption monitoring function becomes operational when configured as Inverter Production + E/I, and the CT Rating is set to a non-zero value.
    To configure the meter for consumption monitoring using SetApp: 1. Make sure that the Meter Function is set to Inverter Production + E/I (default factory setting). 2. Select CT Rating for the meter and enter the current transformer’s rating in amperes (default is 0A). The consumption monitoring
    function becomes operational once the default setting is changed to a non-zero value.
    NOTE
    The CT rating for L3 (used for production metering) is set to 50A by default, and is not configurable.
    3. Select Commissioning RS485-1 Meter x (the meter number), and configure the following settings.
    AC Cable Gauge: 6 – 14 AWG (default is 8 AWG). AC Conduit Length: 0 – 100 feet (default is 20 feet).
    To deactivate the consumption monitoring function using SetApp: 1. To stop consumption monitoring, the user should set the Meter Function to Production.
    NOTE
    Auto-activation is supported only when the meter’s function is set to Inverter Production + E/I.
    To verify that the meter is configured for production and consumption monitoring, using SetApp: 1. From the main menu, select Communication, and verify that Meter1 is connected to RS485-1. 2. Verify that the following settings are configured:
    RS485 Protocol: Modbus (Multi-Device). Function: Inverter Production + E/I. Meter Protocol: SolarEdge. Device ID: 1. Note: ID DIP switch settings on the meter are factory-set to address 1. CT Rating should be set to the current transformer’s rating in amperes.
    3. All other settings mentioned above, including: AC cable gauge and AC conduit length, should be properly configured.

    8
    Monitoring the Meter
    LEDS
    The meter utilizes the LEDs on the top of the unit in order to indicate current status.
    NOTE
    The LEDs can be viewed only when the DC Safety Unit is open.

    LED #
    1 2 3

    Color
    Green Yellow Yellow

    Function
    Operational status RS485 Modbus communication Energy management

    Indication
    Blinking ON/OFF – normal operation Blinking ON/OFF – communication OK Single blink when the meter reads an energy change of ~1 kwH.

    Meter Specification
    Meter type Electrical Characteristics Nominal voltage range
    Operating voltage range
    AC Frequency Grid supported
    Power consumption Over-voltage protection Accuracy RGM (CT3, L1/L2)
    Accuracy E/I meter (CT1/CT2, L1/L2) (1) 1-5% of 200A CT (split core), 1-2.5% of 400A CT (split core)

    Production and Consumption
    208 to 240 (line-to-line) 120 to 277 (line-to-neutral) 187 to 264 (line-to-line) 108 to 305 (line-to-neutral) 55 to 65 Single phase (split phase) with or without neutral: L1 / L2 / N / PE and L1 / L2 / PE < 3W CAT III @ 600V ANSI C12.20 class 0.5 (with Solid core CT) IEC 62053-22 Class 0.5S; IEC 62053-23 Class 2
    ±2

    5-100% of 200A CT (split core),

    ±1

    2.5-100% of 400A CT(split core)

    1-4% of 250A CT (flexible coil), 4-100% of 250A CT (flexible coil) Current Transformer Nominal Input CT1/CT2 (at CT Rated Current)

    ±6(2) ±5(2)
    CT1, CT2: 0.333

    Applicable CT1/CT2 (E/I input)
    Dimensions Internal/External
    225A slim CT See the datasheet for specifications:

    Split core: 200A, 225A, 400A Flexible coil: 250A, 400A
    For Rated RMS Current: 200 A
    Internal: 0.8 x 0.8 / 20 x 20 External: 2.4 x 2.4 / 61 x 61

    For Rated RMS Current: 400 A
    Internal: 1.26 x 1.83 / 32 x 46.5 External: 3.3 x 4.5 / 83.4 x 114

    https://sparc.canto.global/direct/document/16u5j230st7iffp72oi3u9cv3d/ck75U8tdRs8gxNGiEAi8kte6TGg/origin al?content-type=application%2Fpdf&name=Current+Transformer_DS_ROW.pdf

    9
    Vac Vac Hz W
    %
    Nominal Vac RMS Inch/mm

    Communication

    Physical port

    3 wire terminal block

    Interface

    RS485 half-duplex, 3 wires (A, B, Gnd)

    Protocol

    MODBUS RTU

    Register update resolution

    Power register < 200

    ms

    All other registers < 4

    Sec

    10

    Mechanical Meter mounting Connectors Wire AWG/cross section range AC voltage Terminal Block Communication Terminal Block Current Transformer Terminal Block Operating Temperature Range Certifications Safety Immunity
    Emissions

    Inverter DIN rail, built-in Euroblock-style pluggable terminal blocks
    up to 12 / 2.5
    24 / 0.2 to 14 / 2 24 / 0.2 to 14 / 2 -40 to +140 / -40 to +60
    UL 61010-1; CAN/CSA-C22.2 No. 61010-1-04; IEC 61010-1 EN 61326: 2002; EN 61000-4-2; EN 61000-4-3; EN 61000-4-4; EN 61000-4-5; EN 61000-4-6; EN 61000-4-11 FCC Part 15, Class B; EN 55022: 1994, Class B

    (1) Relates to energy measurement (2) When using a flexible coil CT with an accuracy-level range of ±5%

    11
    AWG/mm2 AWG/mm2 AWG/mm2 oF/oC

    References

  • Documents / Resouces

    Download manual
    Here you can download full pdf version of manual, it may contain additional safety instructions, warranty information, FCC rules, etc.


    Related Manuals