SeeLess SLA-1G-2G-3G-4G In-Wall Plaster

ATTENTION! – Always make sure the power has been cut off before attempting any installation
- ROUGH-IN INSTALLATION:
Make sure the electrical box is centered. Adjust the SeeLess black perforated aluminum brackets, to either 1/2“, 5/8”, or 3/4″ line. Caddy bars are recommended for easy mounting between studs (*not supplied by SeeLess). Verify studs are level so that the platform is leveled with the drywall. Flat-headed screws are recommended (Pre-drill SeeLess brackets for rounded screws). *Don’t over-screw when using a power drill to avoid cracking the gypsum
- POST-INSTALL DRYWALL INSTALLATION:
Cut in drywall around the platform in the desired location. Level the drywall with the lower line of the joint on the front of the gypsum platform.
- Adjust the SeeLess black perforated aluminum brackets, to either 1/2“, 5/8”, or 3/4″ lines. Insert the SeeLess platform at an angle.

- Level the drywall with the lower line of the joint on the front of the gypsum platform. Secure the SeeLess platform using flat-headed drywall screws.

- Cover the inside of the platform with paper or tape to protect the center opening. Apply the fiberglass tape on all four joints around the platform. Patch with drywall compound.

- Sand surface smooth. Apply one coat of primer and wait for it to dry. Apply two coats of paint (it is recommended that you paint inside of the opening).

- Install the device.

- SeeLess suction cups are available to remove the faceplate.

ROUGH-IN INSTALLATION
Telescopic (retractable) caddy brackets and drywall screws are not included.
When mounting a SeeLess Platform:
- Make sure the electrical box is centered to your gypsum platform before installing drywall. The box can be loosened and moved to center it.

- Measure your desired distance between the two studs.
- Caddy bars are recommended for easy mounting between studs.

- Verify studs are level by using a straightedge across the platform. Furr out each side, if necessary, so that the platform is leveled with the drywall.

- Check the thickness of drywall to be installed and adjust the SeeLess black perforated aluminum brackets, to either 1/2“, 5/8”, or 3/4″ line (holes are perforated to the standard market perforation size).

- Check the level and height of the plaster platform. Screw caddy brackets to each stud at the appropriate height.
- Line up and screw the black perforated brackets on the SeeLess platform to the caddy crossbars. *Don’t over screw when using a power drill to avoid cracking the gypsum. We recommend using two flat-headed screws.

- If you are using rounded screws, predrilling the brackets is recommended.
- Put straightedge across studs and flush out the outer edge of the plaster box to it, then check the level.
- Gypsum has center lines marked on each side of the platform to help with laser marker alignment.

- For knockout and wiring, press on the soft pre-punched 1/2” and 3/4″ knockouts on the junction box. Re-check the electrical box to ensure it is centered with the gypsum platform after wiring.

POST INSTALL DRYWALL INSTRUCTIONS
- Cut in drywall around the platform.

- Level the drywall with the lower line of the joint on the front of the gypsum platform.

- Make sure that the laser center markers are evenly centered on all sides along the drywall.
- Cover the inside of the platform with paper or tape to protect the center opening
- Apply the fiberglass tape on all four joints around the platform.

- We recommend using the Fast Set Lite 20 (or 40 depending on available time).

- The recommended joint compound to use is the Green Dot topping by Westpac Materials.
- Once the first layer of the mud dries, sand-down with 120 grit sandpaper. When the second layer of mud dries, we recommend using 200-grit sandpaper. Then, when the third layer of mud dries, use 220 grit sandpaper.

- Apply one coat of primer and wait for it to dry.
- Apply two coats of paint. (it is recommended that you paint inside of the opening).

1 866 442 5377 5222 Venice Boulevard,
Los Angeles, CA 90019
www.SeeLess.com