INSTALL GUIDE — HEAVY DUTY VEHICLES
APPLICABLE FOR 6-PIN AND 9-PIN CONNECTORS
![]()
![]()
Locate the vehicle’s diagnostic port and detach it from its original location.
![]()
Connect the Samsara cable. The vehicle’s diagnostics remain accessible via the unconnected port.
![]()
Fasten unconnected diagnostics port to vehicle’s original port location.
![]()
Plug the Samsara cable gateway connector into the gateway. It will click when fully inserted. Remove the rubber safety cover on the USB port to connect the USB plug into the gateway. For best results, do not cross cables or wrap around the gateway.
![]()
Fasten connected gateway in a secure position. Verify the gateway indicator light turns green, this could take 1–3 minutes.